The shop drawing submittal process on condo and multifamily projects, step by step

How a shop drawing submittal moves from subcontractor to GC to architect on a condo or multifamily job, what reviewers check, why sets come back, how to plan it.

Aurum Render · · 8 min read
The shop drawing submittal process on condo and multifamily projects, step by step

On a condominium or multifamily building, very little gets fabricated until its shop drawings come back approved. Facade panels, windows, railings, millwork, stairs: each trade draws how it will build its share, and each set goes up the chain for review before anyone orders material. The submittal process is how those drawings travel, and it is where a lot of schedule is quietly gained or lost.

This guide follows one facade submittal from the subcontractor to the architect and back, with sheets from a sample set we drew for a seven-story mixed-use condominium. It covers who does what, what reviewers look for, why sets are returned and how to plan the time.

The rules come from the contract and Division 01

On projects that use the AIA’s general conditions, A201, shop drawings are drawings, diagrams, schedules and other data specially prepared for the Work by the contractor or a subcontractor. They are submittals, not contract documents: they show how the contractor proposes to build what the drawings and the specification describe. The AIA’s own guide to submittals says the architect reviews them for the limited purpose of checking conformance with the project’s design concept.

The practical rules for a specific job sit in Division 01 of the project manual, in the submittal procedures section. That section sets the format, the transmittal, the stamp the general contractor must apply, how many days the design team has to review, and how resubmittals are handled. Each technical section, such as the one for the cladding system, then lists the submittals that section requires. Read both before drawing anything; a set that ignores the required format can be returned without being reviewed at all.

Step 1: the subcontractor prepares the set

The trade installing the work, or a drafting studio working for it, prepares the drawings from the architectural set, the specification section and the manufacturer’s installation details. For a rainscreen or panel facade, a complete submittal usually has:

  • layout elevations on the building’s grid lines, every panel marked and dimensioned;
  • enlarged elevations and sections where the layout changes, at corners, balconies, the podium and the parapet;
  • details of every junction, with each layer named from the sheathing to the panel face;
  • a panel schedule and, where the supplier needs one, a cut list from the stock sheet sizes;
  • product data and samples, where the specification asks for them.
Sample shop drawing sheet SD-301: enlarged elevation of one bay over levels 2 to 4, with panel layout dimensions in feet and inches, floor elevations and callouts to the joint, head and sill details

Two things belong in the set before it leaves the subcontractor. The first is field dimensions where the structure is already built, because a layout drawn only from the architect’s dimensions will not fit the frame as it stands. The second is any design the contract has delegated to the contractor. Where the specification makes the contractor responsible for designing the attachment of the cladding or its support framing, a licensed engineer engaged by the contractor does that design and seals it, and the shop drawings show the engineer’s attachments and spacing.

Step 2: the general contractor reviews and stamps it

The GC checks the set against the contract before it goes any further: the right product, the full scope, dimensions that agree with the other trades’ work, nothing that clashes with the windows or the waterproofing. Under A201, the contractor’s submission is its representation that it has done that checking. A GC that forwards sets without reading them only moves the problems to the architect’s desk, where they cost more review time.

The GC also logs the submittal, so everyone can see what is out, with whom and since when. On a large building the submittal log is one of the most watched documents on the project.

Step 3: the architect and consultants review it

The architect, and any consultant whose work the set touches, reviews it against the design. A facade submittal often goes to the envelope consultant too, and where there are sealed calculations, the engineer of record looks at how they affect the structure.

The set comes back with an action. The words vary by firm, but they usually amount to one of four: no exceptions taken; make corrections noted; revise and resubmit; rejected. The first two let fabrication proceed, the second with the noted changes made. The last two mean another round.

Close-up of a sample detail at 3 inches to the foot: the horizontal joint at the floor line, with the slab edge, hat-channel furring cavity, Z-flashing, 3/8 inch open joint and fasteners labeled

Why submittals come back

Most returns trace to the same short list:

  • Undeclared deviations. A different panel, a moved joint or another manufacturer’s flashing drawn without comment. A departure needs to be pointed out in writing at submission; otherwise approval does not cover it.
  • Missing interfaces. The typical joints are drawn, but not the corner at the balcony, the meeting with the storefront or the head of the garage opening.
  • Numbers that don’t agree. A schedule that no longer matches the elevations after a revision, or dimensions that do not tie back to grid lines and floor elevations.
  • Incomplete transmittals. No GC stamp, no product data, or no answer to comments from the previous round.
Close-up of a sample panel schedule: six panel types with widths, heights, quantities and square footage, and the first stock sheets of the cut list

Step 4: resubmittal

A resubmittal should take the reviewer less time than the first review, not more. That means a response to every comment, in writing, a cloud and a revision mark on everything that changed, and an unchanged sheet left unchanged. Reviewers trust a set where they can see exactly what moved.

Planning the time

Work backward from the date material has to be ordered, which on a facade is set by the supplier’s lead time. From that date, take off the review period the specification allows for each round, at least one resubmittal, the GC’s own review and the drafting itself. Then add the time it takes to get answers from the design team, because questions raised while drawing are the most common reason a first issue slips.

The sooner the subcontractor has the architectural set, the specification section and the manufacturer’s details together, the sooner those questions surface. Drawing the set from a 3D model of the facade helps too: the layout, the details and the schedule come from one source, so a change made for one comment updates every sheet it touches.

Our shop drawings page explains how we draw a facade or millwork package for submittal and what we need to quote it, and what shop drawings are covers the basics of a set.

FAQ

Questions buyers ask

Who is responsible for the accuracy of shop drawings?

The contractor and the subcontractor that prepared them. The architect reviews submittals for conformance with the design concept, and that review is not a check of every dimension or quantity, so field-verified dimensions and correct counts stay with the trade even after an approval stamp.

What does 'revise and resubmit' mean on a returned submittal?

That the reviewer found enough wrong, or enough missing, that the work should not proceed on that set. The subcontractor revises to every comment, clouds each change, answers each comment in writing and submits again. Fabrication waits until a later set comes back approved or approved as noted.

Can a shop drawing change the design?

Not by itself. A departure from the contract documents has to be pointed out in writing when the set is submitted and accepted in writing by the architect; otherwise the approval does not cover it. Flag every substitution, cloud it on the sheet and list it in the transmittal.

Do shop drawings need an engineer's stamp?

Only where the work they show includes design the contract delegates to the contractor, such as the attachment of a cladding system or its support framing. Then a licensed engineer engaged by the contractor designs that part and seals the calculations and drawings for it. The rest of the set is drafting and carries no seal.

Start a project

Get a fixed quote

A fixed price, scope and delivery date by the next business morning. No deposit for registered businesses.

Drawings can follow by email once we reply, or use the full quote form to add timing, budget and more detail.

We use these details only to reply to your inquiry and prepare a quote. The form also tells us how you reached us — the site that referred you, the pages you viewed and your approximate location — so we know what brings inquiries. See our privacy policy.